Sofitel London Heathrow

Sofitel London Heathrow

An innovative HV project delivery with a nine month payback.

Programme

When the Sofitel London Heathrow hotel explored options to migrate from the Airport’s privately owned and operated High Voltage (HV) electricity system to a new supplier, significant potential energy cost reductions were identified, but only if a series of complex engineering challenges could be overcome.

Although there was a connection point to a new HV network only 200m away, a conventional ‘excavation and reinstatement’ approach to lay the cable was rejected on economic grounds. So DragonIS provided a directional drilling solution, using topographical data mapped by ground penetrating radar. This meant negotiating a host of critical – and densely located – underground services, including fuel delivery pipes, hydrant mains, fibre optic cabling, 11 and 33kV electricity cables and a gas feed.  

At the hotel site, a new intake substation was installed, along with HV switchgear, to take the feed from the DNO (SSE).

Outcome

As a result of DragonIS’s innovative design and programme of works, the hotel achieved project payback in just nine months, thanks to much reduced energy costs.


A proven track record

9 months payback thanks to reduced energy costs.

ROI achieved in 9 months.

1 new intake substation installed with HV switchgear.


Keeping the Lights on in Knoydart Scotland

Knoydart is situated between Loch Nevis and Loch Hourn on the west coast of Scotland and relies exclusively on locally-generated power because it is not connected to the National Grid. Programme In recent years, the community has faced repeated instances […]

READ MORE
National Gas Emergency ServiceElectricity fault?