Sofitel London Heathrow

Sofitel London Heathrow

An innovative HV project delivery with a nine month payback.

Programme

When the Sofitel London Heathrow hotel explored options to migrate from the Airport’s privately owned and operated High Voltage (HV) electricity system to a new supplier, significant potential energy cost reductions were identified, but only if a series of complex engineering challenges could be overcome.

Although there was a connection point to a new HV network only 200m away, a conventional ‘excavation and reinstatement’ approach to lay the cable was rejected on economic grounds. So DragonIS provided a directional drilling solution, using topographical data mapped by ground penetrating radar. This meant negotiating a host of critical – and densely located – underground services, including fuel delivery pipes, hydrant mains, fibre optic cabling, 11 and 33kV electricity cables and a gas feed.  

At the hotel site, a new intake substation was installed, along with HV switchgear, to take the feed from the DNO (SSE).

Outcome

As a result of DragonIS’s innovative design and programme of works, the hotel achieved project payback in just nine months, thanks to much reduced energy costs.


A proven track record

9 months payback thanks to reduced energy costs.

ROI achieved in 9 months.

1 new intake substation installed with HV switchgear.


University of Keele

Design and installation of an elevated pressure gas meter rig to support the expansion of the University of Keele campus. Programme Over recent years, the University of Keele has embarked on a far-reaching expansion programme for its campus and business […]

READ MORE

The Pirbright Institute

The Pirbright Institute undertakes research into viral diseases in livestock and is part-way through a £250m programme. A gas supply was needed to new buildings on site, which would require a branch saddle connection to the gas main, laying 3100m […]

READ MORE
National Gas Emergency ServiceElectricity fault?